December 20, 2023 By Kevin Y. Chen
Categories: Regulation , Infrastructure , Clean Energy , Energy Policy , Grid Modernization
On December 19, 2023, the U.S. Department of Energy (DOE) released long-awaited final guidance on its process to designate National Interest Electric Transmission Corridors (commonly referred to as “NIETCs,” pronounced \NIT-sees\). Once designated, these corridors will bolster federal permitting authority over transmission projects in areas most in need of additional capacity.
As we've previously noted, DOE has statutory authority to designate NIETCs in transmission-constrained or congested geographic areas, within which the Federal Energy Regulatory Commission (FERC) may issue permits for construction or modification of electric transmission facilities. Transmission permitting authority has traditionally been held by the states, so NIETC designation could have broader effects with respect to the siting and permitting of transmission projects.
According to the final guidance, DOE will designate NIETCs based on four criteria:
Further, DOE will engage in a four-phase process to identify potential NIETCs. During this process, DOE plans to:
The initial window for submitting information and recommendations closes on February 2, 2024 at 5:00 PM. Submissions can be made by emailing NIETC@hq.doe.gov. DOE will hold a webinar about this initial public comment period on January 3, 2024 at 1:00 PM EST.
DOE expects to issue its preliminary list of potential NIETC designations and open a second public comment period on the preliminary list in spring 2024.